Phase 1 Wastewater Treatment Plant Project
Project Name:
     Phase 1 Wastewater Treatment Plant Improvements Project

General Area:
     Northeast and Southwest Wastewater Treatment Plants



Project Description:

The City of Oskaloosa has determined that improvements are needed to the Northeast and Southwest Wastewater Treatment Facilities. The project includes replacing the existing grit removal systems, replacing the digester boiler, replacing the mechanical air handling systems, and structure rehabilitation of the wet wells as well as other associated improvements. The plans for the project can be seen below.

Construction Plans


Project Locations:

Work will be performed at the Northeast and Southwest Wastewater Treatment Facilities. View the location map below for detailed locations for projects.

Location Map


Project Benefits:
This project will benefit the City by ensuring that DNR effluent standards are met as well as improving the safety of workers in the treatment facilities

Project Status:
Bids for this project were opened on February 8, 2019, and will be acted upon by the City Council on March 4, 2019. 

Engineers Estimate of Project Cost:
Design Costs:                                                                $133,200.00
Inspection Costs:                                                           $143,900.00
Construction Costs:                                                    $1,290,000.00
Total Estimated Construction Cost:                       $1,595,900.00                   

Construction Start Date:
Spring 2019
Construction End Date:
June 2020

 
 