Click to Home

Go To Search
RSSPrint
B Avenue West Paving Project
Project Name:
      B Avenue West Paving Project

Project Location:
      B Avenue West from North L Street to 230' west of North L Street

Project Description:
  • New 22 foot wide concrete street from North L Street to 230' west of North L Street. 
  • New 5' wide sidewalk and storm sewer improvements.
  • Upgrade all sidewalk ramps to meet current ADA accessibility standards.
  • Construction scheduled to begin in October 2018.

Project Benefits:
This benefits of this project include new concrete street pavement, sanitary and storm sewer improvements, water service improvements, and ADA accessible sidewalk and ramps. 


Project Status:
The City Council, at their meeting on June 18, 2018, approved a contract with Garden & Associates to design the B Avenue West Paving Project.   Garden and Associates Inc. has prepared plans and specifications for this project.  Three (3) bids were received and opened on Thursday, September 6, 2018, at 10:00 a.m., with the low bid being submitted by TK Concrete, Inc. in the amount of $158,640.00.  These bids as well as the final plans will be presented to the City Council for a public hearing on Monday, September 17, 2018.  If the project is awarded, construction will begin on or about October 15, 2018.  The allowable work completion time for this project is 25 working days. 

Plans for this project can be found below:
B Avenue West Paving Project Plans


Estimated Project Costs:
Design:                                    $22,250.00
Inspection:                               Not yet approved
Construction:                           $174,640.00 [$158,640.00 (construction contract) + 16,000 (contingency)]*

Total Project Cost                    $196,890.00*              

*contingent upon council approval on September 17, 2018 and will increase after including cost for inspection

Design Phase Start Date:
06/18/2018
Design Phase End Date (Estimated):
09/04/2018
Construction Phase Start Date:
Early October
Construction Phase End Date (Estimated):
End of November

Project Completion (Estimated):
November 2018
 
 


If you have any questions about this project, please contact the Public Works Department at (641) 673-7472.


Stay ConnectedTwitterFacebook