Project Name:
Downtown Resurfacing Project
Project Locations:
High Avenue, 1st Avenue, 2nd Avenue East, South 1st Street, South 2nd Street and South 3rd Street
Project Description:
The scope of work on this project includes 3,555 LF of asphalt mill and overlay, pavement markings, and related construction items for the downtown area.
Project Benefits/Plans:
These improvements focus mainly on the downtown or business district.
Link to Plans
Road Map
Project Status:
This project was awarded at the Oskaloosa City Council meeting April 4, 2022 to Norris Asphalt Paving Co., LC for $534,730 along with $53,500 in contingency for a total of $588,230. This project has a total of 45 working days with a completion date of September 15, 2022.
Project Cost Summary:
$599,696.87 (project final cost)
Construction Start Date
July 18, 2022
Construction End Date
October 3, 2022
If you have any questions about this project, please contact the Public Works Department at (641) 673-7472.