Project Description

The scope of this project included the removal and replacement of 800 feet of existing curb and gutter along with 40 feet of full width removal and replacement.

Project Benefits

The improvements will help direct storm sewer runoff to storm sewer intakes.

Project Locations

North 6th Street from B Avenue to A Avenue and South 6th Street from 2nd Avenue to 3rd Avenue

Project Status

JC Construction LLC completed this project on July 2nd

Estimated Project Cost:

Construction Cost (Estimated): $88,842.00

                 Project Total (Final): $64,575.11

Construction Start Date 06/08/2020

Construction End Date

07/02/2020