North J Street Pavement Project

Project Name
North J Street Pavement Project

General Area
North J Street between A Avenue West and High Avenue West


Project Description
  • The scope of this project included the removal and replacement of 735 square yards of concrete pavement.   


Project Benefits
The existing road surface was needing to be lowered after the placement of new curb and gutter along the east side..

Project Locations
  • North J Street between A Avenue West and High Avenue West

Project Status
Blommer's Construction Inc. completed this project on November 6th.

Estimated Project Cost:
Construction Cost (Estimated): $46,513.50

                 Project Total (Final):                   $46,651.33

Construction Start Date11/02/2020
Construction End Date
11/06/2020