Project Name
Phase 1 Wastewater Treatment Plant Improvements Project
General Area
Northeast and Southwest Wastewater Treatment Plants
Project Description
The City of Oskaloosa has determined that improvements are needed to the Northeast and Southwest Wastewater Treatment Facilities. The project includes replacing the existing grit removal systems, replacing the digester boiler, replacing the mechanical air handling systems, and structure rehabilitation of the wet wells as well as other associated improvements. The plans for the project can be seen below.
Construction Plans (PDF)
Project Locations
Work will be performed at the Northeast and Southwest Wastewater Treatment Facilities. View the location map below for detailed locations for projects.
Location Map (PDF)
Project Benefits
This project will benefit the City by ensuring that DNR effluent standards are met as well as improving the safety of workers in the treatment facilities
Project Status
Bids for this project were opened on February 8, 2019, and will be acted upon by the City Council on March 4, 2019.
Engineers Estimate of Project Cost
Design Costs: $133,200.00
Inspection Costs: $143,900.00
Construction Costs: $1,290,000.00
Total Estimated Construction Cost (Final): $1,335,793.40
Construction Start Date
Spring 2019
Construction End Date
May 2020