3rd Avenue East Pavement Rehabilitation Project
General Area
3rd Avenue East from Hope Street to South 17th Street (US 23)
Project Description
- The scope of this project included the removal and replacement of 2,679 square yards of concrete pavement.
- The total project cost was $186,054.50 (2,679 square yards) of which $21,079.50 (324 square yards) was in additional work.
- TK Concrete, Inc. started this project on July 6th with 35 working days.
3rd Avenue East Plans
Project Benefits
The current existing pavement surface was showing several signs of degradation, this project will upgrade the pavement surface and the existing infrastructure.
Project Locations
- 3rd Avenue East from Hope Street to South 17th Street (US 23)
Project Status
TK Concrete, Inc. started the project on July 6, 2020 and substantially completed the construction on August 7, 2020.
Estimated Project Cost:
Construction Cost (Estimated): $164,975.00
Project Total (Final): $186,054.50
Construction Start Date
07/06/2020 |
Construction End Date
11/06/2020 |
Project Completion
This project was substantially completed on August 7, 2020. |
|
|
|