3rd Avenue East Pavement Rehabilitation Project

Project Name


     3rd Avenue East Pavement Rehabilitation Project

General Area
     3rd Avenue East from Hope Street to South 17th Street (US 23)
     



Project Description

  • The scope of this project included the removal and replacement of 2,679 square yards of concrete pavement.   
  • The total project cost was $186,054.50 (2,679 square yards) of which $21,079.50 (324 square yards) was in additional work.
  • TK Concrete, Inc. started this project on July 6th with 35 working days.
         3rd Avenue East Plans

Project Benefits


The current existing pavement surface was showing several signs of degradation, this project will upgrade the pavement surface and the existing infrastructure.   

Project Locations


  • 3rd Avenue East from Hope Street to South 17th Street (US 23)

Project Status


TK Concrete, Inc. started the project on July 6, 2020 and substantially completed the construction on August 7, 2020.   

Estimated Project Cost:
     Construction Cost (Estimated):                   $164,975.00
    
                     Project Total (Final):                   $186,054.50

Construction Start Date


07/06/2020

Construction End Date

11/06/2020

Project Completion

This project was substantially completed on August 7, 2020. 
 
 

If you have any questions about this project, please contact the Public Works Department at (641) 673-7472.