Phase 2 Sanitary Sewer System Improvements
There will be a public hearing held for this project at 6:00 PM on Monday, April 2, 2018 in the Council Chambers, City Hall, 220 South Market, Oskaloosa, Iowa in accordance with the provisions of Chapter 384, Code of Iowa. At the hearing, the City will receive and consider any objections made by any interested party to the Plans and Specifications, proposed form of ocntract, and the estimate of cost for the project.

Project Name:
     Phase 2 Sanitary Sewer System Improvements

General Area:

Project Description:
Through an inspection process, it has been determined that the sanitary and storm sewer several areas of the City of Oskaloosa has begun to fail, causing high inflow and infiltration.  The phase 2 project is the second of several projects that have been planned in order to provide effective and reliable sanitary and storm sewer service to residents. The project includes sewer pipe reconstruction (approximately 2,600 LF), sewer pipe lining (approximately 9,800 LF), manhole reconstruction (15 manholes), manhole rehabilitation (approximately 330 LF), and manhole invert repairs (33 manholes). The preliminary plans for the project can be viewed below:

Project Plans

Project Locations:

Work will be performed in various locations throughout the city. View the location maps below for detailed locations for projects.

Location Map 1
Location Map 2
Location Map 3

Project Benefits:
Residents currently using sanitary and storm sewer services in these areas will benefit directly as a result of this project.  This project will also reduce the inflow and infiltration of excess water into wastewater treatment facilities, which will reduce long-term operating and maintenance costs.

Project Status:
This project is currently in the bidding phase, with the bid opening scheduled for March 15, 2018, and a public hearing will be held on April 2, 2018. Construction is planned to begin on or about May 1, weather permitting. The construction is divided into two divisions, with Division 1 being allotted 100 working days and including primarily sanitary sewer replacement projects and division 2 allotted 125 working days and including primarily sanitary sewer rehabilitation projects.

Estimated Project Cost:
Sanitary Sewer Reconstruction:                             $813,280.50
Sanitary Sewer Rehabilitation  :                          $1,124,915.00
Total Estimated Construction Cost:                $1,938,195.50  

Construction Start Date:
Construction End Date:


If you have any questions about this project, please contact the Public Works Department at (641) 673-7472.