1st Avenue Rehabilitation Project
Project Name:
     1st Avenue East Rehabilitation Project

Project Location:
     1st Avenue East from South 1st Street to South 3rd Street


Project Description:
  • The scope of this project includes milling the existing pavement, asphalt overlay, concrete pavement reconstruction, full depth concrete patching, repairing concrete curb & gutter sections, ADA accessible sidewalk and ramp reconstruction, and storm sewer improvements.  
  • This project will be completed in two phases. The 1st phase involves concrete repairs and storm sewer improvements.  This phase is currently in progress and is expected be completed by May 26, 2017. 
  • The 2nd phase consisted of an asphalt mill and overlay. This phase began May 8, 2017 and was completed on May 9, 2017.

Project Benefits:

This project improved the existing roadway with a new asphalt overlay, full depth concrete repairs, and curb and gutter replacement. In addition, new ADA sidewalk ramps improved pedestrian mobility.  Click on the links below to view the project plans for Phase 1 and Phase 2.

1st Avenue East Concrete Pavement Rehabilitation Project Plans (Phase 1)
1st Avenue East Asphalt Pavement Rehabilitation Project Plans (Phase 2)


Project Status:
  • Norris Asphalt was contracted to complete the asphalt rehabilitation portion of this project for $68,650 with an additional contingency of $5,000.  On Monday, May 8, 2017, Norris Asphalt began the 1st Avenue East Asphalt Pavement Rehabilitation Project and completed it on Tuesday, May 9, 2017.  The street was re-opened to traffic on Wednesday, May 10, 2017.  The total cost for this project was approximately $70,700.  
  • Popson Construction is separately contracted to complete the concrete portion of this construction project for $29,000 with an additional contingency of $3,000.  Apart from the sidewalk ramps on the SW corner of 1st Avenue East and South 2nd Street and some minor repairs, Popson Construction has completed the 1st Avenue East Concrete Rehabilitation Project. Popson Construction is scheduled to return the week of May 15th to finish the concrete portion of this project. 

Estimated Project Cost:
Concrete Repairs:          $29,300
Asphalt Overlay:            $70,700
Total Estimated Cost:  $100,000

Concrete (Phase 1) Start Date:
04/10/2017
Concrete (Phase 1) End Date:
05/26/2017
Asphalt (Phase 2) Start Date:
05/08/2017
Asphalt (Phase 2) End Date:
05/09/2017


If you have any questions about this project, please contact the Public Works Department at (641) 673-7472.