Burlington Road Reconstruction Project
Project Name:
Burlington Road Reconstruction Project

Project Location:
Burlington Road from South 17th Street (Hwy 23) to the City Limits


Project Description:
  • The scope of this project includes new concrete street with curb and gutter and storm sewer improvements.  
  • This project has been awarded to Metro Pavers Inc.
  • Construction activity is anticipated to begin in the summer of 2018.

Project Benefits:
This section of Burlington Road is currently paved with chip seal.  The new concrete street will provide a more durable pavement surface.  In addition, storm sewer improvements will reduce water drainage problems along this section of roadway. 
                 

Project Status:
This project will be funded by an 80/20 matching funds grant.  The grant was awarded to the City of Oskaloosa by the Iowa DOT.  This project has an anticipated summer of 2018 construction start date.  It will be constructed as part of University Park's Burlington Road Reconstruction Project.  Construction activity is expected to last a total of 95 working days. 

Estimated Project Cost:
           City Portion (20% of the project):     $37,000
          DOT Portion (80% of the project):   $148,000
                               Total Project Cost:    $185,000

Phase Start Date
05/07/2018
Phase End Date
10/31/2018

Project Completion
The project is expected to be completed in the fall of 2018.  