3rd Avenue East Reconstruction Project
Project Name
     3rd Avenue East Reconstruction Project

General Area
     3rd Avenue East from Market Street to 7th Street, South 1st Street from 3rd Avenue to Rock Island Avenue, and South 6th Street from 3rd Avenue to 1st Avenue.
     


Project Description
  • The scope of this project includes new concrete street with curb and gutter, storm water improvements, water main improvements, sanitary sewer improvements, new ADA accessible sidewalk ramps, new concrete alley approaches, and driveway pavement replacement.   
  • The total project cost was $1,815,398 with 1,632,948.02 towards construction and $182,450.00 towards design and inspection.
  • Cornerstone Excavating Inc. used 155 working days to start the construction on April 13, 2015 and substantially complete the construction on April 20, 2016.
         3rd Avenue East Plans

Project Benefits
The current block curb and brick and asphalt pavement will be reconstructed with new concrete to provide a more durable and smooth street surface.  Water drainage and flow will be improved along this section of 3rd Avenue with new storm sewer pipes and intakes.  All sidewalk ramps will be reconstructed to ADA standards to provide greater accessibility.  The alley approaches will also be reconstructed in concrete for greater accessibility.  Water main pipe and sanitary sewer pipe and manholes will be constructed as needed in order to upgrade the existing infrastructure.   

Project Locations
  • 3rd Avenue East from Market Street to 7th Street (Street Reconstruction)
  • South 1st Street from 3rd Avenue to Rock Island Avenue (Storm Sewer)
  • South 6th Street from 3rd Avenue to 1st Avenue (Storm Sewer) 

Project Status
Cornerstone Excavating Inc. used 155 working days to start the construction on April 13, 2015 and substantially complete the construction on April 20, 2016.   

Estimated Project Cost:
     Construction Cost:                   $1,632,948.02
     Design & Inspection Services: $   182,500.00
     Project Total (Estimated):     $1,632,948.02

Phase Start Date
04/13/2015
Phase End Date
4/20/2016

Project Completion
This project was substantially completed on April 20, 2016. 
 
 

If you have any questions about this project, please contact the Public Works Department at (641) 673-7472.