2017 Sewer Improvements Project
Project Name
     2017 Sanitary & Storm Sewer Improvements Project

General Area
     Northwest, Southeast, and Southwest Quadrants


Project Description:
This project involves the replacement of approximately 4,400 feet of sanitary sewer and 2,300 feet of storm sewer at the locations listed below.  Through an inspection process, it has been determined that the sanitary and storm sewer in these areas has begun to fail, causing high inflow and infiltration.  In order to provide effective and reliable sanitary and storm sewer service to residents, the sewers at the following locations will be replaced and/or relocated. 

Project Locations:
  1. Sanitary sewer along and east of South L/M Street from High Avenue to Arbor Trace Drive.
  2. Sanitary sewer from North Market Street to west of Penn Blvd.
  3. Sanitary sewer along 5th Avenue between South B Street and South 1st Street.
  4. Sanitary sewer along 6th Street between A Avenue East and High Avenue East.
  5. Storm sewer along South L/M Street from A Avenue West to 3rd Avenue West.
  6. Sanitary and storm sewer at the community stadium.

2017 Sanitary & Storm Sewer Improvements Project Plans

Project Benefits:
Residents currently using sanitary and storm sewer services in these areas will benefit directly as a result of this project.  This project will also reduce the inflow and infiltration of excess water into wastewater treatment facilities, which will reduce long-term operating and maintenance costs.

Project Status:
The project is currently out for bid.  The bidding closed on Thursday, February 24th, 2017 at 10:00 a.m. and the results will be presented to the City Council on Monday, March 6th, 2017.  This project will begin in early to mid-April of 2017 and will continue for approximately 210 working days.

Estimated Project Cost:
The preliminary engineering cost estimate for this project is $2,132,053.00.                                     

Construction Phase Start Date:
04/01/2017 (Estimated)
Construction Phase End Date:
05/31/2018 (Estimated)

Project Completion:
Construction is proposed to commence in early to mid-April of 2017 and be completed by the end of May 2018.  The construction will be substantially completed at each location before work will begin at the next location.  The order of completion of the project will be determined by the contractor who is awarded the project.

If you have any questions about this project, please contact the Public Works Department at (641) 673-7472.